NW Retreaders, Portland, OR
Evaluation of existing pre-engineered metal building for conformance with current code
Customer: Steel Structures Support Services
Project Phase: Completed in 2008.
TC TRANS, Blaine, WA 10,080 sq. ft.
Evaluation of pre-engineered metal building mezzanine addition and field modifications
Customer: Roosendaal-Honcoop Construction, Inc.
Project Phase: Completed in 2008.
Reliant Processing, LTD, Maricopa, AZ
Evaluation of pre-engineered metal building for building modifications
Customer: Western Metal Buildings
Project Phase: Completed in 2008.
MEE Industries, Inc., Azusa, CA
New Construction: pre-engineered metal building design
Customer: Knight Building Systems, Inc.
Project Phase: Completed in 2008.
Hesperia WArehouse, Hesperia, CA
Structural Analysis of Existing pre-engineered metal building/Field Modifications
Customer: VP Buildings, Inc.
Project Phase: Completed in 2008.
Pacific Ethanol, Stockton, CA
Building Upcode: pre-engineered metal building
Customer: VP Buildings, Inc.
Project Phase: Completed in 2008.
Vehicle Maintenance Facility, Palms, CA
Structural Analysis of Existing pre-engineered metal building/Field Modifications
Customer: PRE-FAB Builders
Project Phase: Completed in 2007.
NP, Boom Maintenance Facility, Blaine, WA
Structural Analysis of Existing pre-engineered metal building/Field Modifications
Customer: VP Buildings, Inc.
Project Phase: Completed in 2007.
G.F. Construction Building, Los Banos, CA 10,000 sq. ft.
Structural Evaluation of Existing Building/Field Modifications
Customer: VP Buildings, Inc.
Project Phase: Currently under construction.
FedEx Ground Building, Eugene, OR 48,437 sq. ft.
Structural Analysis of Existing Building/Field Modifications
Customer: VP Buildings, Inc.
Project Phase: Currently under construction.
American
Tire Warehouse, Eagle River, Alaska
New Construction: pre-engineered metal
building framing system.
Customer: Ron’s General
Project Phase: Completed in 2000
|